RESPONSES TO RFQs ARE NOT OFFERS: DON’T MAKE THE RFQ MISTAKE

Request for Quotations (“RFQs”) may create a “no-win” situation for a government contractor. That is particularly true when the contractor misses the delivery date, as in TTF, LLC, ASBCA Nos. 58495, 58516, 2013 BCA ¶ 35403. The supplier has made what is called “the RFQ mistake.”

Request-for-Quotations-RFQs

Follow the scenario below, which is abbreviated, but is essentially what TTF faced:

  • Agency issues an RFQ for 37 aircraft fuselage fairings.
  • TTF submits a responsive quote to the agency, which negotiates the price down slightly
  • Agency issues a unilateral Purchase Order (“PO”). The PO states that TTF is not required to sign the PO in order to indicate acceptance. TTF does not sign it.
  • Delivery date specified in the PO is 180 days after award
  • TTF cannot comply with the delivery date, but sends a letter requesting a 120-day extension due to “vendor delays.” The Contracting Officer doesn’t respond to the letter.
  • The Contracting Officer sends TTF a letter stating that its failure to deliver means the PO has lapsed, and she is canceling the PO. No termination action is necessary—TTF is out of luck

What’s going on here? The Federal Acquisition Regulation (“FAR”) is driving the result. FAR 2.101 recognizes two types of offers: (1) responses to invitations for bids in sealed bidding are offers called bids or sealed bids; (2) responses to requests for proposals in negotiated procurement are offers called proposals. However, responses to requests for quotations are not offers but are quotations or quotes. The legal effect of quotations is described in FAR 13.004 as follows:

A quotation is not an offer and cannot be accepted by the Government to form a binding contract. Therefore, issuance by the Government of an order in response to a supplier’s quotation does not establish a contract. The order is an offer by the Government to the supplier to buy certain supplies or services upon specified terms and conditions. A contract is established when the supplier accepts the offer.

When the Government issues a Purchase Order in response to a quotation that order is merely an offer by the Government –a contract is established only when the supplier accepts the offer. The supplier may indicate its acceptance of the order in writing, or the supplier may indicate acceptance by furnishing the supplies or services ordered or by proceeding with the work to the point where substantial performance has occurred. Unless the contractor has signed and accepted the purchase order, the Government may, at any time before acceptance occurs, withdraw, amend, or cancel its offer.

So when TTF got its order (the Purchase Order), it had two ways to accept it:

(1) by signing the PO and returning it to the agency as an “acceptance” or,

(2) by not signing, but by proceeding with the work (and delivering the supplies)

Do you see the mistake? The Agency sent the purchase order with the statement that “the Contractor is not required to sign the PO in order to indicate acceptance,” and TTF didn’t sign it. (Acceptance will only occur later, if the contractor delivers the goods). If the contractor had signed it, there would have been a complete contract at the outset. Of course, if the contractor had accepted it, the government still could have terminated the contract for default, but there would have been a contract in place. In TTF (and many earlier cases like this), the Board held that there was no contract for it to consider, and the PO had lapsed by its own terms (the non-delivery of the goods). The contractor got no relief at all.

Don’t make the RFQ Mistake.

If you receive a purchase order, sign it, accept it, and send your acceptance back to the agency. You will then have a contract. Then you must perform, or have valid reasons for non-performance. By accepting the order in writing, you prevent the agency from withdrawing, amending, or canceling its offer at any time before acceptance occurs later–upon delivery of the goods or services.

Related Post

Why the Latest CR Isn’t All You Want It To Be

While Congress has passed a Continuing Resolution (CR) that will keep some government agencies open until January 19th and others until February 2nd, contractors should not view this CR as “business as usual”. The timing, “laddered” approach, and disagreements on...

Read your Contract and Remember the Rules

In two recent cases, one before the Civilian Board of Contract Appeals (“CBCA”) and the other at the Federal Circuit, the contractors either failed to read their contract, or they ignored some basic contracting rules, like the plain meaning rule in contract...